Current status
Our initial round of consultation is closed. We received a large volume of complex feedback. We are taking the time to consider it carefully.
Timeline of events
| Date | Activity | Status |
|---|---|---|
| March to June 2026 | Initial consultation | Completed |
| June to mid-October 2026 | Consider feedback and develop proposed changes to Framework | Underway |
| Early November 2026 | Pharmac SLT and Board consider proposed changes | Not started |
| Late November 2026 | Round two of consultation | Not started |
| February 2027 | Second round of consultation closes | Not started |
| March to June 2027 | Consider feedback and final decisions made | Not started |